Storm Water Drainage Project Scheduled

The City of Kewanee Public Works Department will be beginning a storm drainage project that is scheduled to start the week of 6/5/17 in the West Oak/Elliott, West Oak/South Park, and South Park/West Prospect Street areas.

 The project will start at the Oak and Elliott intersection and will extend west on Oak to Park Street, then south on Park Street to Prospect and then west on Prospect for about 300 feet. 

 Streets in these areas will be closed from time to time during construction and the traveling public is requested to avoid these areas. Every effort will be made to accommodate the local residents’ access to their houses. Through traffic will not be allowed on most days while work is taking place. The project is anticipated to last 6 weeks.

 If questions or concerns, please contact City Hall at 852-2611.